Written by Royal Polaris Office
|
|
Wednesday, 14 May 2008 11:22 |
Tuesday May 13, 2008
Chaos does not even start to describe all that is happening aboard the Royal
Polaris.
1. Jesus, Roy, Cole, Anthony, Big D, plus 4 painters sanding marine
bondo filler from hull 7:30am to 6:00pm
2. 2 men grinding on holes where engines were removed
3. last 2 mains in boat
4. 2 electricians, Billy, Aaron, Raphael, Tom Dale and another helper
all working in engine room. Getting engines in the boat is only the tip of
the iceberg. Now all 5 engines need to be wired and hooked to main panel,
provide fuel lines, water line and exhausts
5. Coast Guard bottom inspection completed in 3 hours and American
Bureau of shipping inspection completed
6. Eddie cleaning out water tank to prepare for re placement of 2'x4"
piece of aluminum
7. Steve Russow our carpenter preparing and installing new dash in
bridge for high tech instruments for all 5 engines
8. Rick Beck from Honor Marine installed new Furuno 1100 Fathometer.
Sonar hoist dropped out of boat for service
9. Danny, a friend of Frank's is working on:
a. Speakers in staterooms
b. Reading lamps
c. Drawer slides - installing new ones so the drawers slide properly
d. Fixing all staterooms doors so they fit tighter eliminating the
'chattering'
10. Steve and Frank are 'chasing' parts as needed by all on boat
Tuesday May 13, 2008
Chaos does not even start to describe all that is happening
aboard the Royal Polaris.
Jesus, Roy, Cole, Anthony,
Big D, plus 4 painters sanding marine bondo filler from hull 7:30am to 6:00pm
2 men grinding on holes where engines were removed
last 2 mains in boat
2 electricians, Billy, Aaron,
Raphael, Tom Dale and another helper all working in engine room.
Getting engines in the boat is only the tip of the iceberg. Now all
5 engines need to be wired and hooked to main panel, provide fuel lines,
water line and exhausts
Coast Guard bottom inspection completed in 3 hours and American
Bureau of shipping inspection completed
Eddie cleaning out water tank to prepare for re
placement of 2’x4” piece of aluminum
Steve Russow our carpenter preparing and installing new
dash in bridge for high tech instruments for all 5 engines
Rick Beck from Honor Marine installed new Furuno 1100
Fathometer. Sonar hoist dropped out of boat for service
Danny, a friend of Frank’s is
working on:
Speakers in staterooms
Reading lamps
Drawer slides – installing new ones so the
drawers slide properly
Fixing all staterooms doors so they fit tighter
eliminating the ‘chattering’
10. Steve and Frank are ‘chasing’
parts as needed by all on boat
|